CHAPTER I GENERAL TECHNICAL REQUIREMENTS 1.1 GENERAL DESCRIPTION 1.1.1 JOB A. This work includes the construction of a high-security infectious disease laboratory building at KST Soekarno Cibinong. The term "work" includes the provision of all labor (experts, craftsmen, laborers and others), materials and equipment/equipment needed to carry out the work in question. B. The work must be completed as intended in the RKS, plan drawings, minutes of work explanation meetings and addenda submitted during implementation. C. Included in the scope of work are preparatory work, water work, electricity work, warehouse work and all permits, for this reason the implementing contractor in the total cost bid must take these works into account. D. Payment method refers to a combination of unit price contracts for architecture, structure, electrical and electronics, plumbing with prices that can change according to the actual volume and price adjustments can be made, payments are made based on the actual volume and can be re-measured if there are differences in volume and scope of work and lump sum contracts for mechanical / air conditioning work and Building Management System (BMS) work, namely contracts for the procurement of goods/services with a fixed and fixed price for the entire work within a certain period of time, based on a fixed and fixed price amount, no price adjustments are possible, all risks regarding the implementation of the work are fully the responsibility provider, payment is made based on stages/progress according to the contract provisions, not based on actual volume, and no re-measurements are carried out, even if there are differences in work volume as long as the scope of work does not change. 1.1.2 CONTRACT DOCUMENTS A. Contract Documents that must be complied with by the Contractor consist of: ● Employment Agreement Letter ● Price Offer Letter and Offer Details ● Working/Implementation Drawings ● Work Plan and Requirements ● Addenda submitted by the Field Supervisor/MK during the implementation period B. The contractor is obliged to examine the drawings, RKS and other related contract documents. If there are differences/discrepancies between the RKS and the implementation drawings, or between one drawing and another, the Contractor is obliged to notify/report it to the Employer's Field Supervisor. The technical requirements for drawings and RKS that must be followed are: 1. If there is a difference between the plan drawing and the detailed drawing, then the detailed drawing is followed. 2. If the scale of the drawing does not match the size numbers, then the dimensions with the numbers that are followed, unless there is an error in writing the numbers which will clearly cause construction imperfections/non-conformities, must first obtain a decision from the Supervisory Consultant/MK. 3. If there is a difference between the RKS and the drawing, then the RKS that is followed, unless this occurs due to a writing error, which clearly results in construction damage/weaknesses, must be decided by the Supervising Consultant. 4. The RKS and the picture complement each other if the picture says it is complete and the RKS does not, then the picture must be followed and vice versa. 5. What is meant by RKS and images above are RKS and images after receiving changes/improvements in the work explanation minutes. C. If as a result of the Implementing Contractor's lack of care in carrying out the work, there is imperfection in the construction or failure of the building structure, then the Implementing Contractor must carry out the demolition of the construction that has been carried out and repair/re-implement it after obtaining the decision of the Supervising Consultant without any compensation from other parties. 1.2 SCOPE OF WORK 1.2.1 GENERAL DESCRIPTION A. WORK Detailed Engineering Design (DED) Planning Work for Infectious Disease Laboratory Infrastructure with a High Level of Security (High Containment Infectious Laboratory) at KST Soekarni Cibinong, generally includes standard and non-standard work. B. Technically, this work covers the entire construction process from preparation to cleaning/tidying up the yard, and continues with the maintenance period as determined, including: a. Preparatory Work b. Architectural Jobs c. Mechanical, Electrical, Plumbing Work d. Laboratory Furniture Interior Work e. Other work that is clearly related to the completion of the work mentioned above 1.2.2 MEANS AND METHODS OF WORK A. The contractor is obliged to check the correctness of the work conditions, review the work site, take measurements and consider the entire scope of work required for completion and completeness of the project. B. The contractor must provide labor and experts who are competent and adequate for the type of work being carried out, and will not employ people who are inappropriate or unskilled for the types of work assigned to him. Contractors must always maintain good discipline and rules among their workers/employees C. The installation contractor must place an expert and experienced person in charge of implementation who must always be in the field, who acts as a representative of the Contractor and has the ability to provide technical decisions and who is fully responsible for receiving all instructions that will be given by the Assignee/Planning Consultant. D. The contractor must provide work tools and equipment such as a spirit level, transportation equipment and other equipment necessary for this job. The equipment and supplies must be in good condition. The contractor is obliged to supervise and organize the work with full attention and to the best of his ability. The Contractor is fully responsible for all implementation methods, methods, techniques, sequences and procedures, as well as the arrangement of all parts of the work stated in the Contract. E. Shop Drawings (work drawings) must be made by the Contractor before a construction component is carried out. F. The contractor must submit 1 (one) soft copy and as built drawings 2 (two) sets of blueprint drawings/copies. These as-built drawings are complete for all installed installations in this project, along with detailed drawings and cut-out drawings. These as-builts must show the exact location and position of all installation parts. References that can be used include: columns, walls and so on G. Shop Drawings must be approved by the Planning Consultant before the relevant construction elements are implemented. H. Before handing over the first work, the Implementing Contractor must complete the drawings according to the implementation which consist of: ● Drawing of an implementation plan that does not experience changes during implementation. ● Shop drawings as detailed explanations or in the form of pictures of changes. I. The settlement referred to in paragraph g must be interpreted as having obtained the approval of the Supervisor/MK after a careful inspection. J. Drawings according to the implementation and the building use and maintenance book are part of the work that must be submitted at the time of the first handover, deficiencies in this case result in the first handover of work not being able to be carried out. K. Repairs/repairs that must be carried out by the Contractor, if: ● Basic work/construction components that are damaged or found to be imperfect during maintenance implementation. ● Other construction components or environmental conditions outside the main work that are damaged due to construction (for example roads, yards, etc.). L. Field improvements in the form of cleaning the site from materials left over from implementation before the contract period ends, unless they will be reused at a later stage. 1.2.3 MAKING AN IMPLEMENTATION SCHEDULE PLAN A. The Implementing Contractor is obliged to prepare and make an implementation schedule in the form of a barchart which is equipped with a graph of planned achievements based on the work component items in accordance with the offer. B. The preparation of this implementation schedule plan must be completed by the Implementing Contractor no later than 10 days after the start of implementation at the work site. The settlement referred to must already have the approval of the Field Supervisor/MK. C. If within 10 days after the work implementation begins, the Implementing Contractor has not completed preparing the implementation schedule, then the Implementing Contractor must be able to present a temporary implementation schedule for at least the first 2 weeks and the second 2 weeks of the work implementation. D. During the time before the planned implementation schedule is prepared, the Implementing Contractor must carry out his work guided by the weekly implementation plan which must be prepared at the start of implementation. This 2-week implementation schedule must be approved by the Supervisory Consultant. 1.2.4 REPORTS A. Daily and Weekly Reports Contractors are required to make daily, weekly and monthly reports that provide an overview of: Physical activity. • Notes and orders from the Assignee/Planning Consultant delivered verbally or in writing. • Number of incoming/rejected materials. • Number of workers. • Weather conditions, and • Work added/reduced. B. The weekly report is a summary of the daily report and after being signed by the Project Manager must be submitted to the Assignor/Planning Consultant for acknowledgment/approval. C. Test Report The installation contractor must submit to the Assignee/Planning Consultant in 3 (three) copies the preparation of the test form as follows: • Test results for all installation operation requirements • Equipment testing results • Cable test results • and others. All tests and measurements that will be carried out must be witnessed by the Assignee/Planning Consultant. 1.2.5 WARRANTY All equipment, materials and quality of work must be guaranteed for 12 (twelve) months from the date of first delivery. From the first delivery until the warranty period ends, if damage or failure of the installation work occurs, the Contractor is obliged to replace or repair the damage at his own expense. If there is damage to the equipment that needs to be repaired or replaced, the guarantee remains valid from the time of the replacement or repair. If there is damage to the main equipment (for example, the AHU motor catches fire) then the motor must be replaced with a new one and the wiring must not be re-wound. All property and factory premises damaged due to the Contractor's negligence must be repaired to their original condition. 1.2.6 WORK MAINTENANCE AND HANDOVER PERIOD A. The maintenance period for this installation is 6 (six) months from the time of first delivery. B. During this maintenance period, the installation contractor is required to repair and carry out imperfect parts of the work that have not been or have been warned beforehand without any additional costs. C. The contractor must submit complete documents at the time of handover of the first work in the form of: a) As built drawings b) Equipment and control brochures containing, among other things: ● Technical Brochure (Performance, Curves) ● Maintenance Manual ● Manual operation c) Test report data d) Equipment and installation guarantee certificate All points i to point iv must be bundled in one bundle and submitted in 2 (two) sets. 1.2.7 ADDITIONS / REDUCTIONS / CHANGES IN INSTALLATION A. Implementation of installations that deviate from plans that are adapted to field conditions must be consulted first with the Assignee/Consultant who will discuss this with the Planner. B. Material changes, etc., must receive instructions from the Assignor/Consultant in writing before being implemented. And any additional/subtracted/changed work must be approved by the Assignor/Planning Consultant in writing. 1.2.8 MATERIAL TERMS AND CONDITIONS A. The contractor must provide building materials in quantity and quality appropriate to the scope of work carried out. As long as there are no other provisions in this RKS and the Minutes of the Explanatory Meeting. B. If there is a dispute regarding the quality of the materials used, the Field Supervisor has the right to ask the Contractor to have the materials checked at the official Materials Research Center Laboratory at the Contractor's expense. Until there is confirmation of the results of the examination from the Laboratory, the Contractor is not permitted to continue the parts of the work that use these materials. C. Storage of materials must be arranged and carried out in such a way that it does not interfere with the smooth implementation of the work and prevents the materials from being damaged. 1.3 JOB SITUATION AND PREPARATION 1.3.1 SITUATION/LOCATION A. The project location is in the KST Soekarno Hatta Cibinong area. The project location will be handed over to the Contractor as it is at the time of the Explanation Meeting. The contractor should conduct careful research regarding the condition of the structure and roof of the building. B. Inaccuracy or negligence in evaluating field conditions, is entirely the responsibility of the Contractor and cannot be used as a reason to submit a claim/demand. 1.3.2 WATER AND POWER A. The contractor must provide water at his own expense/expenses required to carry out this work, namely: ● Working water for mixing or other purposes that meets the requirements according to the type of work, is clean enough, free from all kinds of dirt and substances such as oil, acid, salt, and so on which can damage or reduce the strength of the construction. ● Clean water for daily needs such as drinking, bathing/defecating and other needs of workers. The quality of the water provided for these purposes must be sufficiently guaranteed. ● The contractor must provide temporary electrical power at his own expense/accounts needed for equipment and lighting and other needs in carrying out this work. Installation of this temporary electrical system must meet applicable requirements. Contractors must arrange and maintain electrical networks and equipment that do not endanger workers in the field. The contractor must also provide temporary lightning protection for safety. 1.3.3 EXHAUST DUCT The contractor must make temporary drainage channels to ensure that the building area is always dry/not wet from rainwater or wastewater. The channel is connected to the nearest ditch/drain or according to the Supervisor's instructions. 1.3.4 PAGE CLEANING ● All obstacles within the land boundary that obstruct the progress of work such as trees, rocks or building debris must be dismantled and cleaned and removed from the building land except for items that are determined to be protected so that they remain intact. ● Demolition must be carried out as carefully as possible to prevent adjacent buildings from being damaged. Used demolition materials are not permitted to be reused and must be transported out of the project yard. 1.4 TECHNICAL INTEGRITY REQUIREMENTS AND PROHIBITION OF DOCUMENT DUPLICATION A. GENERAL PROVISIONS a. Suppliers (Contractors / Vendors) are strictly prohibited from preparing Technical Proposals or Bidding Technical Documents by copying part or all of the contents of the Work Plan and Conditions (RKS), Technical Specifications or Bidding Documents (Selection Documents / KAK / TOR) without adjusting the substance and proof of the proposed product specifications. b. Bidding technical documents must be the result of independent technical preparation and analysis, which describes the Supplier's understanding of system requirements, building characteristics, environmental conditions, as well as the capabilities of the products and technology being offered. c. Any technical information submitted in the proposal must be proven objectively and verifiably through official manufacturer documents such as brochures, catalogues, data sheets, or technical specifications which are publicly available and can be accessed globally via the manufacturer's official website or international technical portal. B. REQUIREMENTS FOR PROOF OF TECHNICAL SPECIFICATIONS a. Providers are required to include an official source link (URL) from the manufacturer or global distributor for each proposed product, indicating conformity between the specifications offered and the specifications required in the RKS. b. The product brochure or data sheet submitted must: ● Have valid product identification (model, type, serial number and manufacturer). ● Shows the main technical parameters according to the RKS, including capacity, power, efficiency, protection rating and minimum performance features. ● In English or Indonesian as recognized by the manufacturer. ● Accompanied by a valid revision date / document code (not a modified version by a third party). c. In the event that discrepancies are found between the technical specifications offered and the manufacturer's official documents, the internationally recognized manufacturer's data sheet will be considered as the correct reference. C. PROHIBITION OF COPYING–PASTING TECHNICAL DOCUMENTS a. Bidding documents that contain descriptions of specifications, implementation methods or technical descriptions that are exactly the same (copy-paste) as the RKS text, without adjustments or proof of technical references, will be deemed not to meet the technical substance (non-responsive) and can be discarded at the technical evaluation stage. b. Points that are prohibited from being copied directly from RKS include: ● Introductory Description, Scope of Work, Standards and References, and Minimum Performance without technical interpretation. ● Description of technical specifications that is not accompanied by proof of reference source. ● Identical implementation method without adjustments to the proposed brand/technology. c. Any text quoted from the RKS document must be reviewed and re-elaborated with a technical narrative that explains how the product being offered meets or exceeds the required criteria. D. TECHNICAL VERIFICATION and CLARIFICATION a. At the technical evaluation stage, the Selection Working Group / Evaluation Committee / Supervisory Consultant has the right to: ● Check the validity of the specifications through the manufacturer's official website. ● Clarify with the official manufacturer / distributor regarding product specifications and availability. ● Reject bids if proposed specifications cannot be independently verified. b. Providers are required to provide source links (internet links), copies of brochures, or technical data sheets (data sheets) for each main product offered c. The Supplier's inability to prove the validity of the proposed technical data is considered a violation of the principle of reliability of the bidding document, and is the basis for the Committee to declare the bid has not passed the technical evaluation (non-compliant). E. FINAL AFFIRMATION 1. With this clause, the RKS and Procurement Technical Documents only function as a minimum reference for performance and system standards, not as text that may be copied into the bid proposal. 2. Technical assessment will focus on: ● Conformity of product specifications with RKS requirements. ● Validity and verifiability of technical data sources. ● Depth of Provider's technical understanding and installation capabilities. 3. Any violation of this provision will be stated in the Technical Evaluation Minutes, and will be the basis for a recommendation to reject the bid in accordance with the provisions of Presidential Regulation Number 16 of 2018 concerning Government Procurement of Goods/Services and its amendments. 1.5 REQUIREMENTS FOR SUBMISSION OF TECHNICAL BID DOCUMENTS Bidders are required to carry out work based on drawings, RKS/technical specifications, and building performance requirements as determined by the PPK. In technical bid, Bidders are required to demonstrate understanding of the document through a logical, realistic and executable implementation method. a. Specifically for critical laboratory systems, bidders are required to submit a general description of the design implementation that shows: understanding of zoning and relationships between laboratory spaces, supporting spaces and related areas; b. understanding the integration of architectural work, HVAC, electrical, plumbing, instrumentation/control, penetration sealing, biosafety cabinets, autoclaves, and other utilities; c. strategy for implementing installation, testing, testing, adjusting and balancing, commissioning, and performance verification; d. strategy to maintain the quality of work so that the results of the implementation meet the design parameters and operational readiness of the facility. Special additional Air Conditioning System (HVAC) For laboratory HVAC systems, Participants are required to submit an implementation overview that at least includes: a. understanding the function of the HVAC system in supporting safety, cleanliness, reliability and control of the laboratory environment b. understanding of zoning, system division, installation sequence, and relationships with other work disciplines; c. understanding of supply and exhaust flow, area separation, temperature and humidity control, control systems, and the relationship of HVAC systems to space performance requirements; d. testing and commissioning strategies, including testing, adjusting and balancing, functional testing, and proving conformity to required design parameters. CHAPTER II GENERAL PROVISIONS 2.1 BACKGROUND This work is part of the construction of an air conditioning (Heating, Ventilation, and Air Conditioning/HVAC) system for the laboratory building which includes the BSL-2 and ABSL-2 Enhanced laboratory areas, along with supporting spaces in one building. HVAC systems in laboratories with a biosafety classification must meet biosafety requirements to prevent exposure, cross-contamination, and maintain a controlled environment during laboratory operations. Taking into account the characteristics of BSL-2 and ABSL-2 Enhanced laboratories, HVAC systems must be designed not only for thermal comfort, but especially to ensure air flow control, chamber pressure, filtration and environmental safety consistently in accordance with applicable international standards. 2.2 AIMS AND OBJECTIVES OF THE WORK The purpose of this work is to provide an HVAC system that is complete, installed, tested, documented, and functions according to biosafety level requirements, both for the laboratory area and supporting rooms in one building. The aim of the work is to ensure that all stages of planning, procurement, installation, integration and commissioning of HVAC systems are carried out in accordance with biosafety standards, technical ventilation standards and the provisions stipulated in this RKS until operating conditions are obtained that meet functional requirements. 2.3 SCOPE OF WORK FOR AIR CONDITIONING SYSTEMS The scope of work includes but is not limited to: A. Procurement of all main equipment and supporting materials for the air system, including Variable Refrigerant Flow or Variable Refrigerant Volume type cooling units, air handling units, air ducts, air flow control equipment, air distribution terminals, air exhaust systems, and laboratory standard filtration devices. B. Carrying out work to install all air conditioning system equipment and networks until they are ready to operate, including cooling equipment, air ducts, air distribution devices, air exhaust systems with high-efficiency particulate air filters, as well as sensor devices and control systems. C. Integration of the air conditioning system with the overall building management system (Building Management System), including connection of control points, monitoring, alarms safety, data recording, and interoperability between other mechanical-electrical subsystems. D. Carrying out the entire series of tests and proof of performance, including acceptance tests at the factory, acceptance tests at the site, capacity adjustment and air flow balance tests, building control system integration tests, as well as preparing a verification summary of the suitability of design, installation and operation for biosafety laboratory facilities E. Submission of all technical documents, final drawings, operation and maintenance manuals, operator training, as well as implementation of final system handover in accordance with applicable regulations. 2.4 CONTRACT SYSTEM AND IMPLEMENTATION METHODS This RKS stipulates a performance-based approach, where detailed HVAC design is entirely the responsibility of the bidder, including determining ducting dimensions, number and type of CAV/VAV, ATD layout, HEPA exhaust design, VRF/VRV cooling capacity, as well as control and interlock schemes. 2.5 SAFETY, SECURITY AND BIOSAFETY COMPLIANCE REQUIREMENTS All work design and implementation must take into account: ● Work safety in mechanical-electrical installations ● Biosafety for BSL-2 and ABSL-2 Enhanced laboratories throughout the work cycle ● Prevention of cross-contamination and exposure ● Space integrity and protection of the laboratory environment during work 2.6 STANDARDS AND MANDATORY REFERENCE DOCUMENTS Participants are required to refer to and comply with the following standards in full: ● WHO Laboratory Biosafety Manual (BSL-2 and ABSL-2) ● NIH Design Requirements Manual (BSL-2 Enhanced/ABSL-2) ● ASHRAE 170 – Ventilation of Healthcare Facilities ● ISO 35001 – Biorisk Management System If there is a conflict between standards, the international biosafety standards and the requirements in this RKS are declared to be of higher priority. CHAPTER III AIR CONDITIONING SYSTEM DESIGN REQUIREMENTS 3.1 PERFORMANCE BASED DESIGN PRINCIPLES The air conditioning system for laboratory buildings must be designed to ensure biosafety, operational comfort, air flow control, and compliance with biosafety standards without locking in a particular design form. Technical values ​​such as capacity, air flow rate, differential pressure, number of supply and exhaust terminals, air channel configuration, and equipment layout are not specified in this RKS, but must be determined, calculated, and proven by bidders based on applicable standards. 3.2 DESIGN RESPONSIBILITIES BY BIDDERS Bidders are required to prepare a complete technical design document containing the design basis, technical justification, calculation methods and detailed engineering drawings for the entire air conditioning system. The proposed design must include at least: ● Design basis report ● Methodology for controlling air flow and zoning laboratory space ● Calculation of supply and exhaust air balance ● Laboratory exhaust design with high-efficiency filters and closed replacement mechanism ● Control system scheme and connection to the building management system ● Review of design compatibility with biosafety standards 3.3 REQUIREMENTS FOR BSL-2 AND ABSL-2 ENHANCED AREAS The design must be able to guarantee that laboratory areas and animal vivariums that are classified as biosafety operate in controlled room conditions in accordance with international standard provisions, including flow control, regulating pressure relations between spaces, preventing recirculation of exhaust air to other areas, as well as filtering exhaust air through high efficiency filters with a closed replacement system. 3.4 FILTRATION OF SUPPLY AIR AND EXHAUST AIR The design must include minimum filtration provisions, namely initial filters and intermediate filters on the supply air to the laboratory area, as well as high-efficiency particulate air filters on all exhaust air from spaces potentially exposed to infectious agents. Installation of a high efficiency particulate filter in the exhaust line must use a closed replacement system (bag-in bag-out) to ensure personnel safety during maintenance. 3.5 VARIABLE REFRIGERANT DISTRIBUTION TYPE COOLING SYSTEM REQUIREMENTS The cooling system used must be of the variable refrigerant delivery type and designed in such a way that it is able to support the performance of laboratory functions, maintain temperature stability, and be compatible with air flow settings, air exhaust systems, and biosafety requirements. 3.6 PRESSURE, AIRFLOW AND ZONING CONTROL REQUIREMENTS Bidders are required to design, determine and prove design values ​​for air pressure between rooms, air flow patterns and air exchange limits in laboratory areas and supporting rooms. The entire design must comply with the provisions of biosafety standards for laboratories as well as applicable international ventilation standards, and must ensure that the pressure relations between zones do not deviate from safe conditions without being detected by the monitoring system. In determining air flow, participants are required to determine the pressure gradient from the clean area to the dirty area to the most dirty area (most contaminated zone) to ensure that there is no backflow of air. The air flow rate in each room must be determined based on the level of biological risk by referring to international standards and ISO 35001, so that both biosafety requirements and researcher work comfort are met. 3.7 REQUIREMENTS FOR INTEGRATION WITH THE BUILDING MANAGEMENT SYSTEM All main components of the air conditioning system, including sensors, actuators, air terminals, exhaust equipment and cooling systems must be fully integrated with the building management system. Integration should at a minimum include pressure value monitoring, filtration status, deviation alarms, operational controls, historical data logging, and tracking capabilities for biosafety audits. 3.8 INTERFACE AND INTEROPERABILITY REQUIREMENTS The design must accommodate the interconnection between mechanical, electrical systems, safety systems and building automation systems, so that no subsystem operates without synchronization with biosafety requirements. CHAPTER IV MATERIAL AND EQUIPMENT REQUIREMENTS 4.1 COOLING UNITS WITH VARIABLE REFRIGERANT DISTRIBUTOR The cooling unit used in this project must be a variable refrigerant delivery system designed to serve all laboratory zones and support spaces within the building. The system must be able to work stably under partial load conditions, support energy efficiency settings, be controlled in an integrated manner, and be compatible with special laboratory air conditioning systems. The cooling unit must be equipped with protection against refrigerant leaks, speed control, and a communication interface that can be integrated with the building management system. 4.2 AIR HANDLING UNITS AND AIR DISTRIBUTION DEVICES Air handling units installed to serve laboratory rooms and supporting rooms must be equipped with: a. Initial stage air filter in the supply air line b. Intermediate stage air filter in the supply air line c. Air distribution terminal device for air supply and return d. Fixed air flow control device or variable air flow control device according to the bidder's design All components must be designed to prevent air leaks and maintain continuous flow in accordance with biosafety principles. 4.3 LABORATORY AIR EXHAUST SYSTEM WITH HIGH EFFICIENCY FILTERS The air exhaust system from the laboratory room must be equipped with a high-efficiency particulate air filter and implemented in a manner that ensures safety when changing the filter media through a closed replacement mechanism. The exhaust air system must be designed to free recirculation into the building and must comply with laboratory biosafety management. Exhaust air from risk areas must be 100% discharged out of the building and directed upwards (vertical discharge), horizontal discharge to the side of the building is not permitted. 4.4 AIR DUCTS, SUPPORTS AND VIBRATION DAMPERS All air ducts, mechanical supports, thermal insulation, and vibration dampers must use materials that do not cause contamination, are resistant to moisture and corrosive substances, as well as meeting fabrication standards for laboratory spaces. Duct connections must be airtight, easy to inspect, and not interfere with controlled air flow. 4.5 SENSOR DEVICES, CONTROLS AND INTEGRATION PANEL Each laboratory zone and supporting room must be equipped with pressure, temperature and air flow sensor devices that can be monitored in real-time. The control panel must allow regulation of the air conditioning system from the building control center, including deviation alarms, data recording and tracking for safety audit purposes. 4.6 INTEGRATION OF THE AIR CONDITIONING SYSTEM WITH THE BUILDING MANAGEMENT SYSTEM All main equipment, sensor devices, actuators, air distribution terminals, exhaust systems and cooling units must be connected to the building management system for the purposes of monitoring, control, alarm, tracking changes and reporting operational conditions. 4.7 QUALITY GUARANTEE REQUIREMENTS FOR MATERIALS AND EQUIPMENT All materials and equipment installed must: ● New and never used before ● Produced by a manufacturer with a track record ● Has factory quality certification and recommended use for laboratory facilities ● Accompanied by technical documents, catalogs and factory test certificates CHAPTER V INSTALLATION AND FIELD IMPLEMENTATION REQUIREMENTS 5.1 METHODS FOR IMPLEMENTING AIR CONDITIONING SYSTEMS Air conditioning system installation work must be carried out by competent personnel, experienced in laboratory facilities, and following work methods that prevent material contamination, equipment damage, air leaks, and disruption to the integrity of the space. Each stage of installation must refer to the approved design document, and no changes are permitted without written approval from the technical supervisor. 5.2 PLACEMENT OF EQUIPMENT AND ACCESS SPACES All cooling units, air handling units, air ducts, air distribution devices, exhaust systems, and control panels must be installed in a position that allows routine maintenance, safety checks, filter replacement, and retesting without requiring major disassembly. The placement of all equipment, channels, service access and maintenance routes must follow the spatial layout and area boundaries as shown in the architectural drawings that are part of this tender document, unless there are technical reasons that require changes and have been approved in writing by the technical supervisor. Service access must be taken into account from the design stage by the bidder and stated in technical drawings that are approved before installation. 5.3 INSTALLATION OF AIR, CONDENSATE AND PROTECTION DUCTS Installation of air ducts must be carried out using techniques that ensure that leaks, microbial colonization or contamination do not occur. Condensate lines must be installed at an adequate slope, equipped with odor collectors and shut-offs if necessary, and protected from the formation of microorganisms. All components in active laboratory areas must be protected during construction to prevent particle contamination. 5.4 INSTALLATION OF AIR EXHAUST SYSTEM AND HIGH EFFICIENCY FILTERS Installation of high-efficiency particulate air filters and laboratory air exhaust equipment with closed replacement systems must be carried out in accordance with the manufacturer's procedures and biosafety guidelines. Work may only be performed by personnel trained and supervised by a technically authorized party. Exhaust equipment must not be connected to any air system other than the laboratory system. 5.5 MARKING, LABELING AND CLEAN CONSTRUCTION DISCIPLINE Each component of the air conditioning system must be clearly labeled for operation and maintenance purposes. Construction in laboratory areas is required to implement work procedures in clean zones, including dust control, regular cleaning, and prohibition of the use of materials that have the potential to be sources of contamination. 5.6 NOISE, VIBRATION AND INTERFERENCE CONTROL Bidders are required to ensure that there is no noise, vibration or other influences that could disrupt laboratory operations or other precision systems. Damping techniques must be planned and proven in the design documentation and verified after installation. CHAPTER VI TESTING AND COMMISSIONING REQUIREMENTS 6.1 ACCEPTANCE TESTING IN THE FACTORY (FACTORY ACCEPTANCE TEST) All major equipment such as variable refrigerant delivery cooling units, air handling units, high efficiency particulate air filter systems and control panels must be accompanied by factory acceptance test results from the manufacturer. The document must show that the equipment has been tested for basic functions before being delivered to the project site. 6.2 SITE ACCEPTANCE TEST After installation is complete and before the system is put into operation, participants are required to carry out acceptance testing on site to ensure that the equipment is installed as designed and functions without mechanical or electrical defects. 6.3 TESTING AIR FLOW ADJUSTMENT AND BALANCE Participants are required to adjust and test the air flow balance in the supply and exhaust system until the flow conditions are obtained according to the design. Tests must include the amount of air flow, uniformity of distribution, and stability of pressure between spaces. 6.4 INTEGRATION TESTING WITH BUILDING MANAGEMENT SYSTEMS Integration testing must be performed to ensure that all control points, safety alarms, room pressure status, air filter status, historical data records, and control logic work as designed through the central building management system. 6.5 LABORATORY SAFETY VERIFICATION (DESIGN, INSTALLATION AND OPERATION) Participants are required to carry out verification stages which include: ● Proving design conformity to biosafety standards (design verification) ● Proving the conformity of the installation to the approved design ● Proving operational readiness through system testing and documentation of results A verification summary should be prepared as part of the commissioning output to ensure the laboratory can be operated to the required biosafety level. 6.6 DOCUMENTATION, REPORTING AND COMPLETION OF COMMISSIONING All test and commissioning results must be stated in an official report containing measurement results data, instruments used, test methods, photographic evidence, and follow-up recommendations if discrepancies are found. The commissioning process is considered complete after all results are received and ratified by the employer. 6.7 TESTING BY INDEPENDENT PARTIES AND FAILURE SCENARIO TESTS Testing the performance of the air conditioning system for this laboratory must follow test methods that refer to international standards and national standards that apply as a basis for certification of the suitability of laboratory facilities. Testing must be carried out by independent testers who have international recognition or accreditation in the field of biosafety laboratories. As part of the verification process, bidders are required to facilitate the implementation of failure scenario testing proposed by independent testing parties, including but not limited to scenarios of air supply failure, air exhaust failure, control system failure, or changes in pressure relationships between spaces. If failure occurs at this testing stage, participants are required to take corrective action until they are declared passed by the independent examiner. All costs, scheduling, technical support, area access, and system readiness for independent testing are part of the participant's obligations and cannot be transferred to the employer. CHAPTER VII TECHNICAL DOCUMENTS AND HANDOVER 7.1 DOCUMENTS TO BE SUBMITTED AT THE BIDDING STAGE Participants are required to submit technical documents as part of the assessment of the feasibility of the offer, including at least: ● Basic report on air conditioning system design along with technical justification ● Air flow design scheme, pressure relationships between spaces, and laboratory zoning ● Concept of integration with building management systems ● Plan installation methods and risk control measures during construction ● List of manufacturers and specifications of major materials and equipment ● Testing and commissioning implementation plan Bids that do not attach the technical documents as intended may be declared not to meet the requirements. 7.2 DOCUMENTS THAT MUST BE SUBMITTED DURING THE EXECUTION OF THE WORK During the implementation phase, participants are required to gradually submit and obtain approval for: a. Detailed engineering drawings (shop drawings) b. Implementation image (as built) after installation is complete c. Installation manual and operating instructions from the manufacturer d. Details of integration points for the air conditioning system with the building management system e. Work safety documents and biosafety compliance during implementation 7.3 FINAL DOCUMENTS AT THE SUBMISSION STAGE At the time of handover of work, participants are required to submit final documents, at least: a. Complete report of test and commissioning results including proof of testing by an independent party b. Summary of design, installation and operation verification according to biosafety standards c. Operation and maintenance guide kit, including filter media replacement instructions and safety procedures d. Regular inspection plans and long-term maintenance recommendations e. Certificates, minutes and statements of test completion from independent examiners 7.4 HANDOVER PROVISIONS AND POST HANDOVER RESPONSIBILITIES Handover of work can only be carried out after all technical, administrative and testing obligations are declared fulfilled. Participants remain responsible for system malfunctions caused by errors in design, installation or material specifications throughout the warranty period. CHAPTER VIII SPECIAL CONTRACT PROVISIONS 8.1 OBLIGATION TO FULFILL BIOSAFETY REQUIREMENTS WITHOUT EXCEPTION All designs, materials, installation, testing and final results of air conditioning systems must comply with the requirements for laboratory biosafety level two and biosafety level two for animals according to international standards. There is no tolerance for deviations that can reduce the level of biosafety. 8.2 PRINCIPLES OF COMPLIANCE WITH THE PERFORMANCE-BASED APPROACH The scope of this document is performance-based, so participants are fully responsible for producing designs that can be technically verified and pass testing. Equating specifications or selecting components without reliable calculations is not permitted. 8.3 TECHNICAL ASSESSMENT BASED ON SPECIFICATIONS AND FUNCTIONAL COMPLIANCE Technical assessment of bids will be based on the suitability of designs, methods and technical specifications to applicable biosafety standards and ventilation standards. The brand or manufacturer's name listed in the offer document is treated only as a reference, while the basis for assessment is technical capability and fulfillment of functions in accordance with the provisions in this document. If differences are found between the technical specifications claimed in the brochure submitted by the participant and the official technical data available globally from the manufacturer, then the participant's design is declared not to meet the requirements and the bid may be declared technically invalid. 8.4 CONSEQUENCES OF FAILURE TO PASS THE TESTING If the results of independent testing or failure scenario testing show non-conformity, participants are required to carry out corrective actions until they are declared passed. All costs for corrections, retesting, and examiner accommodation are the responsibility of the participant without additional payment by the employer. 8.5 Prohibition of Plan Changes Without Approval Any changes to the design, implementation method, installation route, or material substitution after approval must obtain written approval. Unilateral changes constitute a breach of contract and may be subject to administrative action in accordance with applicable regulations. 8.6 ADDITIONAL TERMS Things that have not been stated in this document but are necessary to achieve system function and safety are considered to be included in the participant's obligations, as long as they comply with the standards referred to and do not conflict with statutory provisions. CHAPTER IX TECHNICAL SPECIFICATIONS OF AIR CONDITIONING SYSTEMS 9.1 GENERAL PROVISIONS The air conditioning system in the BSL-2 laboratory zone and ABSL-2 Enhanced vivarium zone must be designed, provided, installed, tested and handed over in a ready-to-operate condition that meets all biosafety, work safety and research integrity requirements. The air conditioning system must ensure that air flow is controlled, pressure relations between spaces are maintained, cross-air mixing between risk zones is prevented, and exhaust air is released through a safe filtering stage without creating a risk of releasing biological agents into the environment. The system must be able to operate stably for 24 hours per day under full load and partial load conditions, including when there is a power interruption or component failure. Any replacement of high efficiency filters on all exhaust lines must use a closed replacement system to prevent exposure to personnel and the environment. No recirculation of air from the laboratory room and vivarium to the supply system is permitted. The air conditioning system must be integrated with the building management system for the purposes of pressure monitoring, air flow control, safety alarms, historical recording and safety audits. The design, implementation and testing of air conditioning systems must be guided by biosafety standards and international ventilation standards that apply to laboratory facilities with a biosafety level. Any deviation from these provisions is not permitted and must be corrected by the provider until operating conditions are achieved that meet biosafety requirements and are declared passed by an independent tester. 9.2 TECHNICAL REQUIREMENTS FOR BSL-2 and ABSL-2 ENHANCED AIR CONDITIONING SYSTEMS 1) Air Flow Requirements and Pressure Relations The air conditioning system must guarantee: ● Air flow moves from clean areas to the dirtiest areas according to biosafety principles. ● There is no backflow from high-risk rooms to lower-risk rooms ● The pressure relationship between the BSL-2 and ABSL-2 Enhanced laboratory spaces is maintained stable at all times, including under conditions of load changes or door movements. ● Differential pressure values ​​must be able to be monitored continuously and recorded through the building management system. ● A pressure loss prevention system must be in place to prevent undetected deviations. 2) Filtration Requirements for Supply Air and Exhaust Air ● The supply air to the laboratory room must be equipped with initial and intermediate stage air filters according to the filtration class applicable to biosafety laboratories. ● Exhaust air from laboratory rooms and vivariums must pass through high-efficiency particulate filters. ● High-efficiency particulate filtration must include a closed replacement system to prevent exposure. ● No recirculation of laboratory air back into the supply system is permitted. ● The exhaust air line must be released to the outside air in a discharge position that does not pose a risk of exposure or re-entrainment. 3) System Integration and Control Requirements ● All pressure, temperature and flow measurement devices must be integrated into the building management system to support monitoring, safety alarms, historical recording and biosafety audits. ● Air conditioning systems must be equipped with automatic controls that prevent critical parameters from drifting undetected ● Mechanical controls and automation must be compatible with electrical systems, emergency protection and power backup systems. ● Operations should not rely on manual intervention to maintain basic laboratory safety. 4) Testing, Verification and Operational Feasibility Requirements ● All design, installation and operation of air conditioning systems must be verified through design testing, installation testing and operational testing before being declared fit for use. ● Mandatory testing includes air flow adjustment and balancing, integration testing with building management systems, as well as robustness testing against failure scenarios. ● Final testing must be carried out by an independent examiner with international recognition. ● The system can only be considered to meet the requirements if all test results are declared passed, proven through official documentation, and submitted as part of the handover process. 5) Requirements for Operational Reliability and Resistance to Disturbances Air conditioning systems in BSL-2 and ABSL-2 Enhanced zones must have a level of reliability that ensures that the biological containment function is not lost in the event of operational disruption. The minimum conditions that must be met include: ● The system must be able to operate stably under full load and partial load conditions without causing deviations in the pressure relations between spaces. ● In the event of failure of any component (e.g. fan, controller, or heat sink), the system must have fail-safe settings that prevent negative pressure loss or air backflow. ● The system should not rely on manual intervention to maintain basic laboratory safety functions; durability must be achieved through engineering design, not operator operations. ● In the event of a power loss, a connected backup system or other protection mechanism must ensure that the pressure connection remains safe until the power supply returns to normal. ● Any post-disturbance recovery mechanism must not result in pressure, flow, or vibration surges that have the potential to harm experimental animals, test materials, or the safety of laboratory personnel. 6) Compliance Requirements with Biosafety and Ventilation Standards All design, installation and testing of air conditioning systems must be proven to meet biosafety standards and laboratory facility ventilation standards. These compliance provisions are mandatory and binding, with details: ● Technical provisions for air conditioning systems must be in accordance with laboratory biosafety guidelines, research laboratory facility design guidelines, ventilation standards for laboratory spaces, as well as applicable national regulations. ● Biosafety requirements must take priority over thermal comfort and energy efficiency requirements if there is a conflict between standards. ● Technical design documents, system calculations and detailed drawings must demonstrate conformity to these standards before work can be carried out. ● Field test, measurement and verification results must show that the installed system functions according to biosafety and ventilation standards, and is supported by valid written evidence. ● Proof of compliance with standards becomes part of the terms of handover; Failure to meet standard requirements requires the provider to make corrections until it is declared passed by the appointed party. 9.3. Air Handling Unit Technical Requirements ● The contractor is obliged to provide, produce, deliver, install, test, commission, and deliver the Air Handling Unit (AHU) system and its accessories until they are fully functional in accordance with the technical requirements, biosafety standards, and minimum performance specified in this document. ● The AHU provided by the Contractor must be specifically designed for infectious laboratory applications (BSL-2 and ABSL-2 Enhanced) with the characteristics of 24/7 continuous operation, high reliability, ease of maintenance, and compliance with all applicable international standards without exception. ● The contractor is obliged to ensure that all AHU components — including casing, filter housing, fan, coil, heater, duct interface, access panels, measuring instruments, and electrical panels are produced and installed with fabrication quality that guarantees tightness air, prevention of cross contamination, material durability, and compatibility with biological risk laboratory environments. ● The contractor is obliged to guarantee that airflow integrity, air-tightness, and thermal and humidity control can be achieved according to the minimum performance specified for each zone. ● All implementation activities, including fabrication, delivery, installation, testing and commissioning of AHU, must be carried out by the Contractor by referring to contract documents, technical standards, approved implementation schedules, as well as applicable safety and biosafety procedures. ● The Contractor is fully responsible for the quality of the work results until the Handover Minutes are issued stating that the AHU has passed inspection, testing and commissioning in accordance with the Acceptance Criteria in this document. The minimum technical specifications for AHU which are divided into 4 zones are as follows: 1. AHU Human Infectious Laboratory Central Corridor Zone ● Minimum total air flow rate: ≥ 28,154 m³/hour ● Filtration : G4 F8 ● Minimum external static pressure : ≥ 750 Pa ● Number of DX coils: 6 rows ● Minimum total cooling capacity : ≥ 640 kWth ● Coil inlet air condition: 33°C / 80%RH ● Coil exit air condition: 11°C / 98%RH ● Minimum electric reheater capacity: ≥ 115 kWth ● Fan control: VSD with continuous performance monitoring 2. AHU Animal Infectious Laboratory Zone ● Minimum total air flow rate: ≥ 20,351 m³/hour ● Filtration : G4 F8 ● Minimum ESP : ≥ 750 Pa ● DX coil: 4 rows ● Minimum cooling capacity : ≥ 463 kWth ● Leaving coil : ≤ 11°C at high humidity ● Minimum heating: ≥ 83 kWth ● Fan controlled by VSD to maintain supply and space pressure difference 3. AHU Animal Holding Zone ● Minimum total air flow rate: ≥ 31,510 m³/hour ● Filtration : G4 F8 ● Minimum ESP : ≥ 750 Pa ● Coil DX : 6 rows ● Minimum cooling capacity : ≥ 760 kWth ● Minimum heating: ≥ 130 kWth ● Minimum two fan motors for operational redundancy 4. AHU Animal Holding Ruminant Zone ● Minimum total air flow rate: ≥ 22,000 m³/hour ● Filtration : G4 F8 ● Minimum ESP : ≥ 750 Pa ● DX coil: 4 rows ● Minimum cooling capacity : ≥ 476 kWth ● Minimum heating: ≥ 82 kWth ● VSD controlled fan, IE-2 motor, IP55 enclosure The following is a grouping of rooms according to zones that have been arranged based on Biosafety levels: